Picture of new terminal
Airport Trail Improvements at YYC // Améliorations sur Airport Trail à YYC

Airport Trail Improvements at YYC // Améliorations sur Airport Trail à YYC

Friday, April 23, 2021 0 Uncategorized

Airport Trail Interchanges Project Update

Map of Airport Trail and Barlow Trail Overpasses

The City of Calgary, with its contractor PCL Construction, are building interchanges on Airport Trail N.E. at 19 Street and Barlow Trail. Work is underway and will continue to 2022. 

Motorists, guests and employees traveling to and from the airport will be encouraged to leave extra time in case of construction delays.

Here’s what you can expect along Airport Trail, east of Deerfoot Trail:

•         Reduced speed limits in construction zones (60 km/h unless otherwise indicated);

 •        Traffic lights at Aero Drive and 19 Street N.E.

•         Narrowed traffic lanes to make space for crews;

•         Intermittent lane closures as needed;

•         Lane shifts, re-alignments and new traffic patterns.

www.calgary.ca/airporttrail will be the central location where stakeholders can get information about construction schedules and detours.


Notice:

Westbound Airport Trail ramp to northbound 19 Street N.E. will be closed to install water and storm lines from April 24 – May 11.

In addition, both northbound and southbound 19 Street N.E. lanes between Airport Trail and 100 Avenue N.E. will be closed from May 1 – May 11. Follow detours signs to Barlow Trail N.E.

For more information and maps visit www.calgary.ca/airporttrail

Avis:

La rampe d’Airport Trail en direction ouest menant à la 19e Rue N.-E. en direction nord sera fermée du 24 avril au 11 mai pour permettre l’installation de collecteurs d’eau pluviale. De plus, toutes les voies de la 19e Rue N.-E. en direction nord et sud seront fermées du 1er au 11 mai entre Airport Trail et la 100 Avenue N.-E. Veuillez suivre les indications pour faire le détour par Barlow Trail N.-E.

Pour plus de renseignements, visitez www.calgary.ca/airporttrail

 


From April 19 - 27 from 8 p.m. to 6 a.m. nightly, beams for the interchanges project will be installed near Barlow Trail and Airport Trail N.E.

Editor's note: Only from April 23, 24 and 26 from 8 p.m. to 6 a.m.:

  • Northbound 19 Street N.E. to eastbound Airport Trail will be closed for safety purposes. Follow detour signs to 100 Avenue N.E.

Throughout the beam installation:

  • All other directions of travel will remain open, but lanes will shift.
  • Reduce speed, watch for signs and follow the instructions of crews.

Calgary Police Services (CPS) will direct traffic at the Barlow Trail and Airport Trail intersection overnight.

For more information visit www.calgary.ca/airporttrail

 

Avis:

Du 19 au 27 avril, on procédera toutes les soirs entre 20 h et 6 h à la pose de poutres pour le projet d’échangeurs près de Barlow Trail N.E. et d’Airport Trail.

Seulement du 21 au 23 avril entre 20 h et 6 h :

  • La 19 Street N.E. en direction nord et Airport Trail en direction est seront fermées pour des raisons de sécurité. Veuillez suivre les indications pour le détour vers la 100 Avenue N.E.

Pendant la pose de poutres:

  • Toutes les autres artères resteront ouvertes, mais les voies seront changées.
  • Ralentissez, surveillez les panneaux et suivez les instructions des équipes.

Le Service de police de Calgary dirigera la circulation à l’intersection de la Barlow Trail N.E. et d’Airport Trail pendant la nuit.

Renseignements : www.calgary.ca/airporttrail

 


Notice:

Map of Barlow Trail Intersection 200 metres east of its current location

Starting on Saturday, Oct. 10, Barlow Trail will shift 200 metres east of its intersection on Airport Trail. The one-year detour will accommodate construction work on the overpass at this location. Eastbound Airport Trail to southbound Barlow Trail will continue to use the existing exit ramp to come to the airport. All other turns will shift to the new intersection 200 metres east. 


Nouvelles du projet d’échangeur sur Airport Trail 

 

Map of Airport Trail and Barlow Trail Overpasses

La Ville de Calgary, avec PCL Construction, commencent la construction de l’échangeur au niveau de la 19e Rue et de Barlow Trail N.E. Les travaux sont effectués et vont durer jusqu’en 2022. Les automobilistes et les visiteurs devront prévoir un peu plus de temps pour se rendre à l’aéroport et en partir, au cas les travaux occasionneraient des retards.

Voici ce à quoi il faudra s’attendre le long d’Airport Trail, à l’est de Deerfoot Trail:

•    Limite de vitesse réduite dans les zones des travaux (60 km/h, sauf indication contraire) Voies plus étroites pour faire de la place aux ouvriers.

•    Feux de circulation à l’angle d’Aero Drive et de la 19e Rue N.-E.

•     Fermetures de voies intermittentes au besoin.

•    Changements et réalignements de voies, et nouveaux trajets

www.calgary.ca/airporttrail sera l’endroit central où les intéressés pourront obtenir de l’information sur le calendrier de construction et les détours.

Avis:

Map of Barlow Trail Intersection 200 metres east of its current location

À compter du samedi 10 octobre, Barlow Trail sera déviée de 200 m à l’est de son intersection avec Airport Trail. Ce détour, qui va durer un an, permettra d’effectuer des travaux de construction sur le viaduc qui passe à cet endroit. Airport Trail Est menant à Barlow Trail Sud continuera d’utiliser la bretelle de sortie existante qui mène à l’aéroport. Tous les autres virages se feront à la nouvelle intersection, 200 m à l’est.

 

 
Print